How to Figure the Large Power Rate


Base Rate

Maximum Load Charge:                                 $10.40 per KVA
Energy Charge:            
  Minimum is the Maximum Load Charge      $0.016540 per KWH

Example

Suppose you used 25,000 KWH and had a maximum load of 200 KVA.

  1. You would take 200 KVA and multiply it by $10.40, which would be $2080.00.
  2. You would hten take the 25,000 KWH and multiply it by $0.016540, which is $413.50.
  3. Your base cost would be the total of these charges plus sales tax, which would be $2,618.18.

Tracker

In addition to the base rate charge there is arate adjustment based upon the cost of purchased power. This can be a positive or negative figure. Because this changes every three months, it is not used in the example. We call this the tracker